{"id":592,"date":"2007-10-09T01:09:54","date_gmt":"2007-10-09T01:09:54","guid":{"rendered":"https:\/\/svapm.org\/2007\/10\/09\/a-common-sense-approach-to-managing-risk\/"},"modified":"2019-08-07T14:37:21","modified_gmt":"2019-08-07T21:37:21","slug":"a-common-sense-approach-to-managing-risk","status":"publish","type":"post","link":"https:\/\/svapm.org\/?p=592","title":{"rendered":"A Common Sense Approach to Managing Risk"},"content":{"rendered":"<p>This weekend I was teaching Project Risk and Opportunity Management at Santa Clara University in the graduate engineering school.\u00a0 As I was watching the students work on their group projects I pondered that this might be a good topic for a blog.\u00a0 How should risks and opportunities be managed from a system perspective especially for large and unprecedented projects?<\/p>\n<p><!--more-->Risk and opportunity are both composed of two elements; probability and consequences.\u00a0 In the case of risk the consequences are perceived to be negative and with opportunity the consequences are believed to be positive.\u00a0 Probabilities are the acknowledgement that there is a lot of uncertainty involved in projects and the likelihood that something will or won&#8217;t happen, can seldom be known for sure.\u00a0 Projects are usually undertaken to either solve a problem or take advantage of an opportunity.\u00a0 The probability that the project even if precisely executed will complete on time, on budget and on performance is typically small.\u00a0 Project management is utilized to increase this probability.\u00a0 So in a sense project management is risk management.<\/p>\n<p>There are three primary phases in developing a\u00a0 risk management plan 1) risk assessment, 2) risk evaluation and 3) risk reduction strategy development and implementation.\u00a0<\/p>\n<p>\u00a0<\/p>\n<p>The first step, risk assessment, is actually the most difficult because it involves identifying all of the potential risks.\u00a0 This is typically done by reflecting on previous projects of this type that the organization has performed.\u00a0 One useful tool for this is a risk checklist.\u00a0 This checklist is developed by collecting the negative experiences that the organization has experienced during its various projects that it would like not to repeat.\u00a0 This could include things like avoiding the use of some materials such as beryllium or having unproven technology development on the critical path or starting a project with negative slack.\u00a0 Use the checklist by considering whether this type of risk is possible or likely on your project.\u00a0 Risks should be documented in an if\/then format.\u00a0 If xyz happens then the result will be such and such.\u00a0 For each if there may be several possible negative consequences that should each be listed.<\/p>\n<p>\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 The second step is risk evaluation.\u00a0 There are numerous ways that this can be accomplished.\u00a0 Everything can be used from the very qualitative (high, medium, low) to the very qualitative (probabilistic risk assessment).\u00a0 Remember the phrase garbage in garbage out when undertaking this step.\u00a0 I tend to use the qualitative approach first especially in the early stages of a project.\u00a0 If you have good statistical data then you can use that but just plucking numbers out of the air does no one any good and can give a very false sense of security or panic.\u00a0 It is important to remember that there are really only two kinds of risks; those that are acceptable and those that are unacceptable.\u00a0 The risk evaluation process in its simplest form involves separating all the risks into these two categories.<\/p>\n<p>\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 The final step of developing and implementing a risk reduction strategy involves taking those risks that are evaluated as being too high and figuring out what can be done about it?\u00a0 There are two basic types of risk reduction strategies; preventative and contingent.\u00a0 In a preventative strategy we try to reduce the probability of the risk event happening such as doing a simulation to validate performance before committing to a design solution.\u00a0 In a contingent strategy we focus on reducing the negative consequences if the risk event should happen.\u00a0 One of the most often used contingent strategies is the use of insurance.\u00a0 Remember that a contingent strategy requires a trigger that will activate it.\u00a0 It also must be crystal clear who is going to take action when the strategy is triggered.<\/p>\n<p>\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 In selecting a risk reduction strategy remember that it may require a combination of both types of strategies to get the risks down to a level where they are acceptable.\u00a0 Also the question of whether the risk reduction strategy makes good economic sense must be answered.\u00a0 Is the amount of risk reduction that we are buying worth the time, money are other resources that we will have to consume to implement it?\u00a0 This is called risk reduction leveraging.\u00a0 The ideal situation is to find a really big risk that can be turned into a small acceptable risk (or no risk at all) cheaply and easily.\u00a0 Sometimes this can be done but other times the strategy may be more difficult to sell and creativity is needed.<\/p>\n<p>\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 Some basic thoughts on risk management planning that I have learned over the years.\u00a0 First, start addressing risk in the early conceptual phase of the project and make risk a key part of the study.\u00a0 Default to the low risk paths when they are available (this is called risk avoidance).\u00a0 Get the entire team involved in identifying and evaluating project risks.\u00a0 Everyone looks at the project differently and sometimes the input from the student intern can be vital.\u00a0 Finally re-evaluate the risks on a regular basis, at least every quarter and see what has changed.\u00a0 Keeping the risk management plan up to date can transform it from a door stop into a vital project management tool.\u00a0 Remember what you don&#8217;t know can kill your project.<\/p>\n<p>\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 I haven&#8217;t spent much time talking about the opportunities but many of the same tools apply you are just looking for positive outcomes instead of negative.\u00a0 The key here is that with planning you can take advantage of opportunities where without this planning you may just watch them pass you by.\u00a0 Like knowing that a key potential customer may be at a conference and putting together a pitch just in case you run into them or being caught by surprise with nothing coherent to say.\u00a0 Little things like this can make the difference between just getting by and hitting a home run. \u00a0There is a saying that luck is the conjunction of hard work and preparation.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>This weekend I was teaching Project Risk and Opportunity Management at Santa Clara University in the graduate engineering school.\u00a0 As [&hellip;]<\/p>\n","protected":false},"author":217,"featured_media":0,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"give_campaign_id":0,"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[7,8,9],"tags":[39],"class_list":["post-592","post","type-post","status-publish","format-standard","hentry","category-goals","category-priorities-2","category-risk-management","tag-best-practices"],"aioseo_notices":[],"jetpack_featured_media_url":"","_links":{"self":[{"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts\/592","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/users\/217"}],"replies":[{"embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=592"}],"version-history":[{"count":1,"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts\/592\/revisions"}],"predecessor-version":[{"id":13843,"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts\/592\/revisions\/13843"}],"wp:attachment":[{"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=592"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=592"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=592"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}