{"id":1354,"date":"2008-10-29T21:20:11","date_gmt":"2008-10-30T04:20:11","guid":{"rendered":"https:\/\/svapm.org\/2008\/10\/29\/project-toolkit-gone-awry\/"},"modified":"2019-08-07T14:33:27","modified_gmt":"2019-08-07T21:33:27","slug":"project-toolkit-gone-awry","status":"publish","type":"post","link":"https:\/\/svapm.org\/?p=1354","title":{"rendered":"Project Toolkit Gone Awry"},"content":{"rendered":"<p align=\"center\"><strong>Horror Story No. 4<\/strong><br \/>\nThis collection of project horror stories would not be complete without a tale concerning:  MICROSOFT PROJECT<\/p>\n<p>Listen now to the saga of <strong>The Project Toolkit Gone Awry<\/strong><\/p>\n<p><img decoding=\"async\" alt=\"TNT\" src=\"https:\/\/svapm.org\/wp-content\/uploads\/2008\/10\/tnt.thumbnail.jpg\" align=\"left\" \/>We were expanding, and expanding FAST.\u00a0 Not five, not ten, but 200 stores were to be built-out, and it was my job to create a project plan for each store, and then roll them all up together into an overall Master Project Plan.<!--more--><\/p>\n<p>I was younger then, and fairly new to project management.\u00a0 So it seemed like a logical move to invoke the PM tool of choice, Microsoft Project, to handle it all.<\/p>\n<p><strong>The Horror:<\/strong> At first, everything seemed to be going fine.\u00a0 I set up a template to serve as a starting point for each store.\u00a0 I then customized the plans as needed to reflect the specifics for each location.\u00a0 No problem.\u00a0<\/p>\n<p>Then it happened.\u00a0 I put in the dependencies and connected them all together to create the Overall Master Plan:  And a monster was truly born!\u00a0<\/p>\n<p><img decoding=\"async\" alt=\"Frankenstein Monster\" src=\"https:\/\/svapm.org\/wp-content\/uploads\/2008\/10\/monster-frankenstein.thumbnail.jpg\" align=\"left\" \/>As I tended to the care and feeding of this creature of my own making, I was soon crushed by it&#8217;s sheer size and burden for daily updates and weekly reporting.\u00a0 My struggle continued to grow as managers who did not use MS Project insisted on updates in Excel.\u00a0 So to meet the demand, I added a custom menu with macros to &#8220;automate&#8221; the conversion process.\u00a0 But this did not go over so well with my team members who had to then install these macros on each machine.\u00a0 Needless to say, I wasn&#8217;t making many friends with such an ugly monster on my back!\u00a0<\/p>\n<p>Finally, I went in one day to update a few dependencies, and threw everything off.\u00a0 What a Nightmare!\u00a0 So I chucked the whole thing and went exclusively to Excel.\u00a0 My good intentions and lack of experience cost me &#8211; and the company &#8211; a great deal of time and anxiety.<\/p>\n<p><strong>Scary Lessons:<\/strong> Microsoft Project has way too many features and functions.\u00a0 When I use it now, I only use about 10% of what is available.\u00a0 I also learned to never create something so complicated that it takes over your life!\u00a0 Get help.\u00a0 And beware of scope creep when it comes to the tools, bells and whistles that you use.<\/p>\n<p>When my friend related\u00a0this tale to me, I\u00a0told them\u00a0they were not alone.\u00a0 I had a similar experience early on in my career, as perhaps you did too.\u00a0 It&#8217;s sort of a rite-of-passage into the world of project management.\u00a0 The good news is that through experiences such as this, we grow older and wiser, and acquire a healthy respect for the AWESOME POWER (for both good and evil) of ALL the tools that we use.<\/p>\n<p><img decoding=\"async\" height=\"96\" alt=\"Atomic Symbol\" src=\"https:\/\/svapm.org\/wp-content\/uploads\/2008\/10\/atomic-symbol2.thumbnail.jpg\" \/><\/p>\n<p>Doug Bedinger<\/p>\n<p><a href=\"http:\/\/www.consulting4results.com\/\">www.consulting4results.com<\/a><\/p>\n<p>Helping individuals, project teams, and whole organizations work better together.<\/p>\n<p>\u00a0<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Horror Story No. 4 This collection of project horror stories would not be complete without a tale concerning: MICROSOFT PROJECT [&hellip;]<\/p>\n","protected":false},"author":104,"featured_media":0,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"give_campaign_id":0,"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[2],"tags":[190,229,345,339,338,36],"class_list":["post-1354","post","type-post","status-publish","format-standard","hentry","category-leadership","tag-mistakes","tag-project-horror-stories","tag-project-management-ease-of-use","tag-project-management-software","tag-project-management-tools","tag-scope-creep"],"aioseo_notices":[],"jetpack_featured_media_url":"","_links":{"self":[{"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts\/1354","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/users\/104"}],"replies":[{"embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=1354"}],"version-history":[{"count":1,"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts\/1354\/revisions"}],"predecessor-version":[{"id":14122,"href":"https:\/\/svapm.org\/index.php?rest_route=\/wp\/v2\/posts\/1354\/revisions\/14122"}],"wp:attachment":[{"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=1354"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=1354"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/svapm.org\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=1354"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}